Project Details
- Oil well soil contamination
- Phase one of the project consisted of 4800 cubic meters of soil remediation
Project Operations
- Ice roads assisted in allowing the team to access the remote, heavily forested site
- Deployment was February 1, 2024. The first phase of the project was complete by the end of March 2024
- Four Enhanced Thermal Conduction (ETC) cells treated 9800 tons of contaminated soil in less than 40 days
Planned Customer Results
- Treatment exceeded specifications
- On-site treatment allowed the soil to remain in place
- Land is returned back to Blueberry River First Nation, Halfway River First Nation, Ft. Nelson First Nation & Prophet River First Nation