Project Details
2,325.79 Tons of soil was treated. Soil was contaminated with M-55 stab detonators, hydrocarbons, and explosives residues.
Project Operations
Project duration was about 1 month (November 7th to December 6th). ETC Technology was utilized.
Planned Customer Results
All laboratory analytical results were below laboratory detection limits (basically non-detect). Project completed with 100% safety record.