British Columbia, Canada

Project Details

  • Located in the Jedney gas field. ~175km northwest of Fort St. John, BC
  • 22,000 tons of impacted soli, from historical operations and spill events
  • Hydrocarbon Impacts: BTEX, VPH and LEPH
  • Abandoned location surrounded by forested public lands

Project Operations

  • Impacted soil excavated and placed in 850 m3 ETC Treatment cell
  • The second treatment cell was constructed while treatment was underway on the primary cell
  • LPG is used for burner fuel
  • Treatment cell turnaround times ranged from 4 to 6 days per cell
  • 24/7 remote temperature and video monitoring ensure treatment goals were reached

Planned Customer Results

  • The treatment was successfully completed in approximately 6 months.
  • All post-treatment samples were below the required standards
  • Treatment commenced in the rainy season and ran into the extreme cold of January
  • Liability was removed and closure was achieved at the site