Project Details
- Located at pipeline transfer station west of Edson, Alberta
- 11,000 tons of impacted soil from historical operations and spill events
- Hydrocarbon impacts: BTEX, VPH and LEPH
- Active pipeline area with the pending expansion of Trans Mountain Pipeline
Project Operations
- Impacted soil excavated and placed in two 850 m3 ETC Treatment cells
- LPG is used for burner fuel
- High levels of ambient Benzene required customized treatment
- Treatment cell turnaround times ranged from 4 to 6 days per cell
- 24/7 remote temperature and video monitoring ensured treatment goals were reached
Planned Customer Results
- The treatment was successfully completed in approximately 6 months
- All post-treatment samples were below required standards
- Contingent liability was removed